TIME & WORK

Time and Work Formula


1.     Work from Days:
If A can do a piece of work in n days, then A's 1 day's work =
  1
.
n

2.     Days from Work:
If A's 1 day's work =
1
,
then A can finish the work in n days.
n

3.     Ratio:
If A is thrice as good a workman as B, then:
Ratio of work done by A and B = 3 : 1.
Ratio of times taken by A and B to finish a work = 1 : 3.

4.     No. of days = total work / work done in 1 day


5.     Relationship between Men and Work

More men         ------- can do ------->             More work

Less men         ------- can do ------->             Less work


6.     Relationship between Work and Time

More work        -------- takes------>               More Time

Less work         -------- takes------>               Less Time


7.     Relationship between Men and Time

More men        ------- can do in ------->          Less Time

Less men          ------- can do in ------->          More Time


8.     If Mpersons can do W1 work in D1 days and M2 persons can do W2 work in D2days, then 
        

9.     If Mpersons can do W1 work in D1 days for h1 hours and M2 persons can do W2work in D2 days for h2 hours, then

 Note:  If works are same, then M1D1h1 = M2D2h2 


10.  If A can do a work in ‘x’ days and B can do the same work in ‘y’ days, then the number of days required to complete the work if A and B work together is




11.  If A can do a work in ‘x’ days and A + B can do the same work in ‘y’ days, then the number of days required to complete the work if B works alone is



           